The Economic Development Authority of Columbia County (EDACC) provided the signed Memorandum of Understanding (MOU) with Kinetic Infrastructure Solutions, a company owned by Google LLC, for the White Oak and Pumpkin Center data center developments.
EDACC approved the agreement on August 26, 2026. I obtained an unsigned copy in September. There are only a few minor changes from the earlier version:
The signed agreement explicitly identifies Kinetic as owned by Google LLC.
The annual cap on bond trustee fees increased from $5,000 to $15,000.
One property parcel number was corrected.
The agreement now includes signatures from both parties.
The major financial terms remain unchanged, including the $45 million annual payment, the $17 billion investment goal, and the 25-year property tax abatement schedule.
The full 39-page signed agreement is available below.